How to restore an old house?
Collecting documentation to start project:
• List of real estate (from the Cadastre)
• Copy of the plan (from the Cadastre)
• Excerpt from the DUP (Civil Bureau - Secretariat for Urbanism)
• Conservation conditions (Directorate for the Protection of Cultural Heritage)
• Urban-technical conditions (civil bureau - Secretariat for Urbanism)
* approximate time limit: 30 - 60 days
Preparation of project documentation:
• Geodetic survey
• Project of existing state
• Conservation project
* approximate time limit: 2 - 6 months
Submission of documentation for building permit
• Conservation project (in 3 printed copies and 7 CDs)
• Revision of the project (for residential buildings over 500 m2 and business buildings)
• Fire study (with audit and consent of the Ministry)
• Consent to the project of the Directorate for the Protection of Cultural Heritage
Required payments to obtain a building permit
• Consent of Water Supply and Sewerage Public Company
• Fee for Regional water supply
• Fee for communal equipment (Directorate for construction and arrangement of the city of Kotor)
* approximate time limit: 15 - 30 days
ISSUANCE OF BUILDING PERMIT!
* Approximate time limit from submission of documentation to obtaining a permit: 30 - 60 days